ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 280 more items below.
| Item | Quantity | R1Amaazz Construction Ohio LLC | R2Shelly & Sands INC | R3Complete General Construction Company | R4George J Igel & CO INC | R5Ruhlin Company | R6Sunesis Construction CO | % of bid |
|---|---|---|---|---|---|---|---|---|
| 452E13020 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P W | 12,550 SY | $58.65 | $64.00 | $70.00 | $69.00 | $79.00 | $102 | 15% |
| 513E10040 STRUCTURAL STEEL MEMBERS, LEVEL 2 | 1 LS | $701,456 | $660,000 | $663,000 | $745,000 | $748,538 | $336,547 | 14% |
| 511E34447 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK, AS PER | 406 CY | $897 | $874 |
| Item | Quantity | R1Amaazz Construction Ohio LLC | R2Shelly & Sands INC | R3Complete General Construction Company | R4George J Igel & CO INC | R5Ruhlin Company | R6Sunesis Construction CO |
|---|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $24,929 | $52,000 | $52,000 | $50,000 | $150,000 | $18,694 |
| 202E23000 PAVEMENT REMOVED | 14,365 SY | $5.35 | $10.00 | $10.00 | $11.00 | $15.00 | $17.38 |
| 202E23010 PAVEMENT REMOVED, ASPHALT | 592 SY | $4.37 | $9.00 | $14.50 | $7.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $965 |
| $840 |
| $825 |
| $1,001 |
| 8% |
| 840E20001 MECHANICALLY STABILIZED EARTH WALL, AS PER PLAN | 6,984 SF | $50.31 | $31.00 | $42.00 | $36.00 | $44.00 | $42.69 | 7% |
| 203E20000 EMBANKMENT | 27,750 CY | $11.47 | $13.00 | $14.00 | $17.00 | $18.00 | $13.40 | 7% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 1,130 CY | $179 | $160 | $160 | $160 | $160 | $160 | 4% |
| 840E23000 SELECT GRANULAR BACKFILL | 3,941 CY | $49.19 | $68.00 | $45.00 | $60.00 | $48.00 | $60.18 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $186,108 | $200,000 | $200,000 | $200,000 | $200,000 | $244,861 | 4% |
| 507E00650 14" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 3,300 FT | $55.96 | $28.00 | $30.00 | $35.00 | $50.00 | $43.69 | 4% |
| 304E20000 AGGREGATE BASE | 3,399 CY | $53.61 | $72.00 | $57.00 | $66.00 | $68.00 | $74.78 | 4% |
| AB2 607E40000 SPECIAL - VANDAL PROTECTION FENCE (DECORATIVE) (AL | 420 FT | $422 | $423 | $445 | $400 | $445 | $465 | 4% |
| 514E00060 FIELD PAINTING STRUCTURAL STEEL, INTERMEDIATE COAT | 17,361 SF | $9.50 | $6.50 | $5.10 | $6.00 | $6.00 | $9.00 | 3% |
| 514E00066 FIELD PAINTING STRUCTURAL STEEL, FINISH COAT | 17,361 SF | $9.50 | $4.00 | $5.10 | $3.80 | $3.80 | $9.00 | 3% |
| 509E10000 EPOXY COATED REINFORCING STEEL | 148,905 LB | $1.08 | $1.20 | $1.25 | $1.18 | $1.40 | $1.19 | 3% |
| 202E11003 STRUCTURE REMOVED, OVER 20 FOOT SPAN, AS PER PLAN | 1 LS | $144,751 | $200,000 | $280,000 | $160,000 | $145,000 | $262,377 | 3% |
| 441E10100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (446), PG | 582 CY | $237 | $195 | $195 | $195 | $195 | $195 | 3% |
| 203E10000 EXCAVATION | 11,057 CY | $11.90 | $11.00 | $9.00 | $15.00 | $17.00 | $11.83 | 3% |
| 511E34463 CLASS QC SCC CONCRETE WITH QC/QA, BRIDGE DECK (PAR | 81 CY | $1,478 | $1,048 | $2,000 | $1,200 | $1,250 | $2,208 | 2% |
| 526E30011 REINFORCED CONCRETE APPROACH SLABS WITH QC/QA (T=1 | 449 SY | $259 | $260 | $275 | $280 | $285 | $306 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $112,626 | $330,000 | $80,000 | $250,000 | $350,000 | $62,164 | 2% |
| $9.00 |
| $11.27 |
| 202E23500 WEARING COURSE REMOVED | 134 SY | $8.20 | $3.00 | $15.00 | $10.00 | $111 | $2.50 |
| 202E30700 CONCRETE BARRIER REMOVED | 64 FT | $24.81 | $19.00 | $40.00 | $43.00 | $20.00 | $53.96 |
| 202E38000 GUARDRAIL REMOVED | 4,900 FT | $2.64 | $2.50 | $2.00 | $2.50 | $2.00 | $2.20 |
| 202E53100 MAILBOX REMOVED | 8 EACH | $83.46 | $85.00 | $60.00 | $45.00 | $111 | $71.44 |
| 202E58100 CATCH BASIN REMOVED | 5 EACH | $144 | $450 | $500 | $200 | $1,700 | $437 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT | 163 FT | $12.45 | $20.00 | $18.00 | $10.00 | $27.07 | $11.62 |
| 202E75000 FENCE REMOVED | 1,250 FT | $4.22 | $4.00 | $2.00 | $4.00 | $2.00 | $2.40 |
| 202E98000 REMOVAL MISC.: SIGN INCLUDING LIGHTS (1919 LANCAST | 1 LS | $969 | $200 | $300 | $300 | $1,000 | $1,500 |
| 202E98000 REMOVAL MISC.: TWO SHEDS PLUS MISCELLANEOUS VEHICL | 1 LS | $1,765 | $750 | $3,000 | $3,000 | $2,500 | $5,572 |
| 202E98000 REMOVAL MISC.: WOOD FENCING (1844 LANCASTER RD.) | 1 LS | $2.11 | $200 | $150 | $200 | $500 | $450 |
| 202E98000 REMOVAL MISC.: WOOD SIGN (1844 LANCASTER RD.) | 1 LS | $839 | $95.00 | $35.00 | $200 | $250 | $500 |
| 202E98100 REMOVAL MISC.: BOLLARDS (1956 LANCASTER RD.) | 3 EACH | $70.56 | $60.00 | $30.00 | $100 | $350 | $114 |
| 202E98100 REMOVAL MISC.: INSPECTION WELL | 1 EACH | $1,206 | $350 | $350 | $230 | $820 | $5,393 |
| 202E98200 REMOVAL MISC.: CONDUIT | 10 FT | $41.97 | $18.00 | $16.00 | $11.00 | $16.00 | $33.57 |
| 202E98300 REMOVAL MISC.: CONCRETE DITCH LINING | 112 SY | $8.05 | $5.00 | $25.00 | $15.00 | $13.00 | $23.12 |
| 203E20001 EMBANKMENT, AS PER PLAN | 5 CY | $60.59 | $100 | $40.00 | $20.00 | $200 | $41.39 |
| 203E65000 SPECIAL - SETTLEMENT PLATFORM | 2 EACH | $727 | $1,950 | $1,500 | $500 | $3,700 | $26,416 |
| 204E10000 SUBGRADE COMPACTION | 1,404 SY | $1.81 | $5.50 | $5.00 | $5.00 | $5.50 | $3.09 |
| 204E13000 EXCAVATION OF SUBGRADE | 425 CY | $10.87 | $24.00 | $20.00 | $15.00 | $120 | $43.98 |
| 204E45000 PROOF ROLLING | 8 HOUR | $159 | $325 | $300 | $160 | $350 | $224 |
| 206E10500 CEMENT | 534 TON | $181 | $172 | $172 | $190 | $180 | $180 |
| 206E11000 CURING COAT | 20,595 SY | $1.11 | $1.05 | $1.05 | $1.00 | $1.00 | $1.50 |
| 206E15010 CEMENT STABILIZED SUBGRADE, 12 INCHES DEEP | 20,595 SY | $2.84 | $2.70 | $4.50 | $3.80 | $3.75 | $4.62 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 565 SY | $10.82 | $20.00 | $10.25 | $20.00 | $10.25 | $8.14 |
| 606E15050 GUARDRAIL, TYPE MGS | 2,762.5 FT | $16.89 | $16.00 | $16.00 | $16.00 | $16.00 | $17.60 |
| 606E26150 ANCHOR ASSEMBLY, MGS TYPE E (NCHRP 350 OR MASH 201 | 5 EACH | $2,270 | $2,150 | $2,245 | $2,150 | $2,245 | $2,320 |
| 606E26500 ANCHOR ASSEMBLY, TYPE T | 5 EACH | $950 | $900 | $975 | $900 | $975 | $975 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 5 EACH | $2,059 | $1,950 | $2,045 | $1,950 | $2,045 | $2,080 |
| 606E35102 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 2 | 3 EACH | $475 | $450 | $450 | $450 | $450 | $500 |
| 606E60028 IMPACT ATTENUATOR, TYPE 2 (BIDIRECTIONAL), 60 MPH, | 2 EACH | $32,466 | $24,750 | $26,325 | $26,840 | $26,325 | $27,220 |
| 607E23000 FENCE, TYPE CLT | 1,645 FT | $23.76 | $22.50 | $20.20 | $22.50 | $20.20 | $21.60 |
| 607E30000 FENCE, SNOW | 745 FT | $4.22 | $6.00 | $3.60 | $5.00 | $3.60 | $4.59 |
| 607E70000 FENCELINE SEEDING AND MULCHING | 1,645 FT | $1.06 | $0.65 | $0.65 | $0.65 | $0.65 | $0.65 |
| 608E10000 4" CONCRETE WALK | 482 SF | $7.92 | $18.00 | $5.50 | $14.00 | $5.00 | $9.82 |
| 622E10061 CONCRETE BARRIER, SINGLE SLOPE, TYPE B, AS PER PLA | 165 FT | $164 | $270 | $170 | $270 | $300 | $284 |
| 622E10161 CONCRETE BARRIER, SINGLE SLOPE, TYPE D, AS PER PLA | 450 FT | $227 | $185 | $160 | $270 | $250 | $292 |
| 622E10161 CONCRETE BARRIER, SINGLE SLOPE, TYPE D, AS PER PLA | 28 FT | $238 | $360 | $225 | $260 | $400 | $347 |
| 622E24841 CONCRETE BARRIER END SECTION, TYPE B, AS PER PLAN | 2 EACH | $5,279 | $8,000 | $7,000 | $9,700 | $3,000 | $8,688 |
| 622E25011 CONCRETE BARRIER END SECTION, TYPE D, REINFORCED, | 2 EACH | $8,446 | $5,000 | $3,500 | $5,300 | $5,000 | $4,328 |
| 622E25011 CONCRETE BARRIER END SECTION, TYPE D, REINFORCED, | 4 EACH | $8,446 | $5,300 | $4,500 | $2,300 | $5,500 | $5,331 |
| 623E40500 REFERENCE MONUMENT | 16 EACH | $514 | $430 | $600 | $840 | $235 | $292 |
| 653E10000 TOPSOIL FURNISHED AND PLACED | 1,308 CY | $22.35 | $19.00 | $20.00 | $28.00 | $12.00 | $58.84 |
| 690E50100 SPECIAL - MAILBOX SUPPORT SYSTEM, SINGLE | 8 EACH | $158 | $150 | $150 | $185 | $135 | $165 |
| 690E50600 SPECIAL - BOLLARD | 3 EACH | $411 | $400 | $685 | $400 | $830 | $730 |
| 690E98200 SPECIAL - DETECTABLE WARNING | 64 SF | $10.56 | $38.00 | $28.00 | $26.00 | $32.00 | $30.00 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $63,348 | $75,500 | $60,000 | $100,000 | $45,220 | $51,170 |
| 601E21050 TIED CONCRETE BLOCK MAT, TYPE 1 | 140.2 SY | $93.00 | $62.00 | $100 | $110 | $170 | $161 |
| 601E21060 TIED CONCRETE BLOCK MAT, TYPE 2 | 6.2 SY | $78.97 | $80.00 | $85.00 | $65.00 | $184 | $158 |
| 601E32200 ROCK CHANNEL PROTECTION, TYPE C WITH FILTER | 5.8 CY | $358 | $225 | $125 | $200 | $183 | $162 |
| 659E00510 SEEDING AND MULCHING, CLASS 2 | 26,701 SY | $0.06 | $0.65 | $0.65 | $2.00 | $0.65 | $1.26 |
| 659E14000 REPAIR SEEDING AND MULCHING | 1,335.1 SY | $0.72 | $0.65 | $0.65 | $0.65 | $0.65 | $0.65 |
| 659E15000 INTER-SEEDING | 1,335.1 SY | $0.72 | $0.35 | $0.35 | $0.35 | $0.35 | $0.35 |
| 659E20000 COMMERCIAL FERTILIZER | 4.4 TON | $473 | $400 | $400 | $400 | $400 | $400 |
| 659E31000 LIME | 5.5 ACRE | $163 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 659E35000 WATER | 167.3 MGAL | $1.06 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 659E40000 MOWING | 721 MSF | $4.22 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 670E00500 SLOPE EROSION PROTECTION | 11,415 SY | $1.35 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 670E00750 DITCH EROSION PROTECTION MAT, TYPE E | 72 SY | $1.68 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 671E15000 EROSION CONTROL MAT, TYPE A | 1,000 SY | $1.34 | $1.65 | $1.65 | $1.65 | $1.65 | $1.65 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $2,640 | $3,000 | $3,000 | $3,000 | $2,500 | $1,575 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $10,136 | $15,550 | $10,000 | $18,000 | $13,680 | $15,390 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $15,713 | $14,500 | $16,000 | $15,000 | $14,882 | $22,301 |
| 832E30000 EROSION CONTROL | 100,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 602E20000 CONCRETE MASONRY | 1.05 CY | $2,026 | $2,500 | $3,600 | $2,300 | $3,300 | $3,985 |
| 605E11100 6" SHALLOW PIPE UNDERDRAINS | 9,222 FT | $7.08 | $10.00 | $9.00 | $9.50 | $10.00 | $9.53 |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 394 FT | $14.42 | $13.00 | $10.25 | $10.00 | $25.00 | $10.12 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 228 FT | $16.43 | $19.00 | $12.50 | $18.00 | $20.00 | $39.18 |
| 611E00900 6" CONDUIT, TYPE B | 123 FT | $15.51 | $25.00 | $25.00 | $25.00 | $27.00 | $19.39 |
| 611E01500 6" CONDUIT, TYPE F | 50 FT | $9.49 | $32.00 | $10.00 | $20.00 | $21.00 | $20.39 |
| 611E04600 12" CONDUIT, TYPE C | 74 FT | $58.46 | $55.00 | $60.00 | $132 | $65.00 | $55.77 |
| 611E05200 12" CONDUIT, TYPE F, 707.05 TYPE C OR 707.21 | 204 FT | $28.89 | $75.00 | $85.00 | $73.00 | $55.00 | $77.97 |
| 611E97400 CONDUIT, MISC.: TYPE B FOR DRAINAGE DISCHARGE CONT | 10 FT | $39.52 | $75.00 | $20.00 | $20.00 | $56.00 | $62.46 |
| 611E97400 CONDUIT, MISC.: TYPE C FOR DRAINAGE DISCHARGE CONT | 10 FT | $20.67 | $60.00 | $15.00 | $61.00 | $48.00 | $58.20 |
| 611E97400 CONDUIT, MISC.: TYPE E FOR DRAINAGE DISCHARGE CONT | 10 FT | $13.13 | $60.00 | $10.00 | $13.00 | $57.00 | $53.94 |
| 611E97400 CONDUIT, MISC.: TYPE F FOR DRAINAGE DISCHARGE CONT | 10 FT | $13.13 | $60.00 | $10.00 | $13.00 | $57.00 | $65.82 |
| 611E98151 CATCH BASIN, NO. 3, AS PER PLAN | 2 EACH | $3,203 | $3,500 | $3,600 | $3,400 | $5,500 | $3,353 |
| 611E98181 CATCH BASIN, NO. 3A, AS PER PLAN | 2 EACH | $2,785 | $3,000 | $2,750 | $2,400 | $4,000 | $2,555 |
| 611E98301 CATCH BASIN, NO. 5, AS PER PLAN | 4 EACH | $2,801 | $5,400 | $3,800 | $4,600 | $5,000 | $3,088 |
| 611E99115 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE D, AS | 4 EACH | $5,691 | $9,000 | $9,750 | $9,100 | $13,000 | $7,678 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 10 EACH | $226 | $250 | $225 | $240 | $350 | $401 |
| 611E99720 INSPECTION WELL | 1 EACH | $991 | $1,300 | $850 | $950 | $2,800 | $659 |
| 613E41200 LOW STRENGTH MORTAR BACKFILL | 30 CY | $129 | $100 | $100 | $90.00 | $130 | $128 |
| 252E01500 FULL DEPTH PAVEMENT SAWING | 2,114 FT | $1.06 | $2.00 | $2.00 | $3.00 | $1.70 | $1.95 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.25" DEEP) | 2,023 SY | $3.17 | $3.00 | $2.92 | $2.92 | $2.92 | $2.92 |
| 254E01000 PAVEMENT PLANING, ASPHALT CONCRETE (1.5" DEEP) | 6,033 SY | $3.05 | $3.00 | $2.92 | $2.92 | $2.92 | $2.92 |
| 407E10000 TACK COAT | 5 GAL | $4.22 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 407E20000 NON-TRACKING TACK COAT | 1,588 GAL | $4.22 | $3.45 | $3.45 | $3.45 | $3.45 | $3.45 |
| 441E10200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 446 (314 CY | $224 | $205 | $205 | $205 | $205 | $205 |
| 441E50100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 31 CY | $380 | $365 | $365 | $365 | $365 | $365 |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (23 CY | $317 | $260 | $260 | $260 | $260 | $260 |
| 452E12050 8" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 44 SY | $92.91 | $175 | $95.00 | $104 | $65.00 | $113 |
| 609E24001 CURB, TYPE 4-A, AS PER PLAN | 44 FT | $23.77 | $43.00 | $95.00 | $85.00 | $80.00 | $70.46 |
| 609E24510 CURB, TYPE 4-C | 73 FT | $30.17 | $40.00 | $38.00 | $35.00 | $35.00 | $30.11 |
| 609E26000 CURB, TYPE 6 | 1,327 FT | $13.38 | $22.00 | $21.00 | $19.00 | $15.00 | $22.50 |
| 823E10000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448) | 4 CY | $633 | $320 | $320 | $320 | $320 | $320 |
| 823E20000 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (5 CY | $633 | $260 | $260 | $260 | $260 | $260 |
| 638E10600 FIRE HYDRANT AND GATE VALVE REMOVED AND RESET | 1 EACH | $2,186 | $3,500 | $2,750 | $1,400 | $12,000 | $3,586 |
| 638E10900 SERVICE BOX ADJUSTED TO GRADE | 1 EACH | $119 | $350 | $100 | $300 | $1,000 | $229 |
| 625E00450 CONNECTION, FUSED PULL APART | 16 EACH | $96.50 | $91.40 | $105 | $93.00 | $93.17 | $92.67 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 38 EACH | $67.73 | $64.20 | $120 | $65.27 | $65.39 | $65.04 |
| 625E10481 LIGHT POLE, DECORATIVE, AS PER PLAN (BRIDGE MOUNTE | 4 EACH | $1,707 | $1,618 | $1,400 | $1,645 | $1,648 | $1,639 |
| 625E10481 LIGHT POLE, DECORATIVE, AS PER PLAN (GROUND MOUNTE | 2 EACH | $2,109 | $2,000 | $1,520 | $2,033 | $2,036 | $2,025 |
| 625E10615 LIGHT POLE ANCHOR BOLTS ON STRUCTURE, AS PER PLAN | 4 EACH | $1,134 | $1,075 | $400 | $1,093 | $1,095 | $1,089 |
| 625E14000 LIGHT POLE FOUNDATION, 24" X 6' DEEP | 2 EACH | $1,677 | $1,590 | $1,800 | $1,616 | $1,619 | $1,610 |
| 625E23302 NO. 6 AWG 2400 VOLT DISTRIBUTION CABLE | 4,884 FT | $2.42 | $2.30 | $1.85 | $2.33 | $2.33 | $2.32 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 1,470 FT | $1.17 | $1.15 | $1.40 | $1.13 | $1.13 | $1.13 |
| 625E25400 CONDUIT, 2", 725.04 | 812 FT | $18.43 | $17.50 | $20.00 | $17.77 | $17.80 | $17.70 |
| 625E25402 CONDUIT, 2", 725.05 | 735 FT | $6.24 | $6.00 | $9.00 | $6.01 | $6.02 | $5.99 |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04 (2") | 345 FT | $39.20 | $37.25 | $40.00 | $37.78 | $37.85 | $37.64 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 6 EACH | $756 | $720 | $540 | $729 | $730 | $726 |
| 625E27403 LUMINAIRE, POST TOP, SOLID STATE (LED), AS PER PLA | 6 EACH | $2,334 | $2,215 | $1,700 | $2,249 | $2,253 | $2,241 |
| 625E29002 TRENCH, 24" DEEP | 735 FT | $14.79 | $14.10 | $10.00 | $14.26 | $14.28 | $14.20 |
| 625E29921 STRUCTURE JUNCTION BOX, AS PER PLAN | 4 EACH | $2,349 | $2,225 | $2,000 | $2,263 | $2,267 | $2,255 |
| 625E30700 PULL BOX, 725.08, 18" | 13 EACH | $777 | $736 | $1,000 | $749 | $750 | $746 |
| 625E32000 GROUND ROD | 2 EACH | $340 | $322 | $260 | $327 | $328 | $326 |
| 625E33000 STRUCTURE GROUNDING SYSTEM | 1 EACH | $5,721 | $5,420 | $6,500 | $5,513 | $5,523 | $5,493 |
| 621E00100 RPM | 183 EACH | $42.23 | $40.75 | $40.75 | $40.00 | $40.00 | $40.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 35 EACH | $7.80 | $15.00 | $10.00 | $10.00 | $7.32 | $16.33 |
| 625E32000 GROUND ROD | 1 EACH | $422 | $400 | $260 | $400 | $250 | $325 |
| 626E00102 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 10 EACH | $13.20 | $12.50 | $7.75 | $12.50 | $7.75 | $7.50 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (BIDIRECTIONAL) | 46 EACH | $8.45 | $8.00 | $7.50 | $8.00 | $7.50 | $7.50 |
| 626E00110 BARRIER REFLECTOR, TYPE 2 (UNIDIRECTIONAL) | 21 EACH | $7.92 | $7.50 | $7.50 | $7.50 | $7.50 | $7.50 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 630 FT | $10.56 | $10.00 | $8.50 | $10.00 | $8.50 | $8.77 |
| 630E04100 GROUND MOUNTED SUPPORT, NO. 4 POST | 146 FT | $12.67 | $12.00 | $10.00 | $12.00 | $10.00 | $10.32 |
| 630E06100 GROUND MOUNTED SUPPORT, NO. 6 POST | 58 FT | $16.36 | $15.50 | $12.50 | $15.50 | $12.50 | $12.90 |
| 630E07600 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W10X12 | 118 FT | $16.89 | $16.00 | $42.50 | $16.00 | $42.50 | $43.86 |
| 630E08200 GROUND MOUNTED SUPPORT, PIPE | 2 EACH | $897 | $850 | $300 | $850 | $300 | $89.37 |
| 630E08600 SIGN POST REFLECTOR | 14 EACH | $44.34 | $42.00 | $45.00 | $42.00 | $45.00 | $46.44 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 6 EACH | $370 | $350 | $375 | $350 | $375 | $387 |
| 630E09050 TRIANGULAR SLIP BASE CONNECTION | 2 EACH | $106 | $100 | $230 | $100 | $230 | $237 |
| 630E20200 OVERHEAD SIGN SUPPORT, TYPE TC-12.30, DESIGN 2 | 1 EACH | $8,974 | $8,500 | $9,820 | $8,500 | $9,820 | $10,135 |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 6 EACH | $581 | $550 | $385 | $550 | $385 | $397 |
| 630E80100 SIGN, FLAT SHEET | 534 SF | $19.53 | $18.50 | $16.50 | $18.50 | $16.50 | $17.03 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 241 SF | $21.12 | $20.00 | $19.00 | $20.00 | $19.00 | $19.61 |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 169 SF | $31.67 | $30.00 | $20.00 | $30.00 | $20.00 | $20.64 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 6 EACH | $1,056 | $1,000 | $975 | $1,000 | $975 | $1,006 |
| 630E84510 RIGID OVERHEAD SIGN SUPPORT FOUNDATION | 1 EACH | $4,223 | $4,000 | $4,620 | $4,000 | $4,620 | $4,768 |
| 630E84600 GROUND MOUNTED PIPE SUPPORT FOUNDATION | 2 EACH | $528 | $500 | $860 | $500 | $860 | $888 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 114 EACH | $15.84 | $15.00 | $10.00 | $15.00 | $10.00 | $10.32 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 11 EACH | $89.74 | $85.00 | $75.00 | $85.00 | $75.00 | $77.40 |
| 630E85200 REMOVAL OF GROUND MOUNTED SIGN AND DELIVERY | 2 EACH | $52.79 | $50.00 | $35.00 | $50.00 | $35.00 | $36.12 |
| 630E85400 REMOVAL OF GROUND MOUNTED MAJOR SIGN AND DISPOSAL | 9 EACH | $163 | $154 | $215 | $154 | $215 | $222 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 84 EACH | $15.84 | $15.00 | $10.00 | $15.00 | $10.00 | $10.32 |
| 630E86050 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DELIVER | 1 EACH | $89.74 | $50.00 | $35.00 | $50.00 | $35.00 | $36.12 |
| 630E86103 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 10 EACH | $528 | $500 | $325 | $500 | $325 | $335 |
| 630E86272 REMOVAL OF GROUND MOUNTED PIPE SUPPORT AND DISPOSA | 2 EACH | $211 | $200 | $145 | $200 | $145 | $150 |
| 630E87400 REMOVAL OF OVERHEAD MOUNTED SIGN AND DISPOSAL | 2 EACH | $211 | $200 | $185 | $200 | $185 | $191 |
| 630E87500 REMOVAL OF POLE MOUNTED SIGN AND DISPOSAL | 8 EACH | $15.84 | $15.00 | $20.00 | $15.00 | $20.00 | $20.64 |
| 630E89707 REMOVAL OF OVERHEAD SIGN SUPPORT AND DISPOSAL, TYP | 2 EACH | $4,223 | $4,000 | $1,525 | $4,000 | $1,525 | $1,574 |
| 631E92001 SIGN FLASHER ASSEMBLY, AS PER PLAN | 1 EACH | $10,155 | $9,620 | $9,000 | $9,618 | $9,804 | $9,751 |
| 642E00300 CENTER LINE, TYPE 1 | 0.5 MILE | $5,944 | $2,150 | $2,150 | $2,150 | $2,150 | $2,308 |
| 644E00100 EDGE LINE, 4" | 0.19 MILE | $5,263 | $4,985 | $4,985 | $4,985 | $4,985 | $5,352 |
| 644E00104 EDGE LINE, 6" | 1.02 MILE | $5,263 | $4,985 | $4,985 | $4,985 | $4,985 | $5,352 |
| 644E00300 CENTER LINE | 0.8 MILE | $5,692 | $5,391 | $5,391 | $5,391 | $5,391 | $5,788 |
| 644E00400 CHANNELIZING LINE, 8" | 670 FT | $1.69 | $1.60 | $1.60 | $1.60 | $1.60 | $1.72 |
| 644E00500 STOP LINE | 122 FT | $6.86 | $6.50 | $6.50 | $6.50 | $6.50 | $6.98 |
| 644E00600 CROSSWALK LINE | 276 FT | $3.17 | $3.00 | $3.00 | $3.00 | $3.00 | $3.22 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 437 FT | $5.28 | $5.00 | $5.00 | $5.00 | $5.00 | $5.37 |
| 644E01300 LANE ARROW | 12 EACH | $93.97 | $89.00 | $89.00 | $89.00 | $89.00 | $95.55 |
| 644E01400 WORD ON PAVEMENT, 72" | 4 EACH | $116 | $110 | $110 | $110 | $110 | $118 |
| 646E10010 EDGE LINE, 6" | 1.44 MILE | $5,168 | $4,895 | $4,895 | $4,895 | $4,895 | $5,255 |
| 646E10200 CENTER LINE | 0.11 MILE | $13,219 | $12,520 | $12,520 | $12,520 | $12,520 | $13,441 |
| 646E10300 CHANNELIZING LINE, 8" | 1,586 FT | $2.06 | $1.95 | $1.95 | $1.95 | $1.95 | $2.09 |
| 646E10400 STOP LINE | 222 FT | $9.98 | $9.45 | $9.45 | $9.45 | $9.45 | $10.15 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 180 FT | $9.98 | $9.45 | $9.45 | $9.45 | $9.45 | $10.15 |
| 646E10800 ISLAND MARKING | 492 SF | $3.75 | $3.55 | $3.55 | $3.55 | $3.55 | $3.81 |
| 646E20300 LANE ARROW | 21 EACH | $185 | $175 | $175 | $175 | $175 | $188 |
| 646E20400 WORD ON PAVEMENT, 72" | 4 EACH | $238 | $225 | $225 | $225 | $225 | $242 |
| 646E20320 WRONG WAY ARROW | 2 EACH | $269 | $225 | $255 | $255 | $255 | $242 |
| 809E60001 CCTV IP-CAMERA SYSTEM, DOME-TYPE, AS PER PLAN | 1 EACH | $6,421 | $6,082 | $8,500 | $6,188 | $6,200 | $6,166 |
| 809E64550 ETHERNET CABLE, OUTDOOR-RATED | 101 FT | $3.86 | $3.70 | $2.60 | $3.72 | $3.73 | $3.71 |
| 625E18401 BRACKET ARM, 20', AS PER PLAN | 6 EACH | $1,496 | $1,420 | $2,900 | $1,442 | $1,445 | $1,437 |
| 625E25502 CONDUIT, 3", 725.05 | 974 FT | $6.96 | $6.60 | $11.50 | $6.71 | $6.72 | $6.68 |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04 (3") | 580 FT | $41.95 | $39.75 | $53.00 | $40.43 | $40.50 | $40.28 |
| 625E29002 TRENCH, 24" DEEP | 709 FT | $14.59 | $13.85 | $10.00 | $14.06 | $14.09 | $14.01 |
| 625E30706 PULL BOX, 725.08, 24" | 15 EACH | $891 | $850 | $1,250 | $859 | $860 | $856 |
| 625E32000 GROUND ROD | 9 EACH | $340 | $325 | $260 | $327 | $328 | $326 |
| 630E79200 SIGN ATTACHMENT ASSEMBLY, MAST ARM | 4 EACH | $333 | $500 | $315 | $500 | $315 | $325 |
| 630E80511 SIGN, STREET NAME, AS PER PLAN | 4 EACH | $422 | $1,250 | $600 | $1,250 | $225 | $200 |
| 632E05007 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 16 EACH | $1,362 | $1,290 | $800 | $1,312 | $1,315 | $1,307 |
| 632E05087 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 4 EACH | $1,771 | $1,680 | $1,160 | $1,707 | $1,710 | $1,700 |
| 632E20721 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, AS PER PLAN | 4 EACH | $781 | $740 | $750 | $753 | $754 | $750 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 20 EACH | $112 | $106 | $45.00 | $108 | $108 | $107 |
| 632E25010 COVERING OF PEDESTRIAN SIGNAL HEAD | 4 EACH | $59.13 | $56.00 | $40.00 | $56.98 | $57.08 | $56.78 |
| 632E26000 PEDESTRIAN PUSHBUTTON | 4 EACH | $373 | $355 | $275 | $360 | $360 | $359 |
| 632E40200 SIGNAL CABLE, 2 CONDUCTOR, NO. 14 AWG | 1,433 FT | $2.80 | $2.65 | $1.75 | $2.70 | $2.70 | $2.69 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 4,343 FT | $3.29 | $3.15 | $2.40 | $3.17 | $3.18 | $3.16 |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 7 EACH | $5,484 | $5,195 | $4,000 | $5,285 | $5,294 | $5,266 |
| 632E64020 PEDESTAL FOUNDATION | 3 EACH | $1,226 | $1,162 | $1,400 | $1,182 | $1,184 | $1,177 |
| 632E68300 POWER CABLE, 3 CONDUCTOR, NO. 6 AWG | 650 FT | $4.27 | $4.05 | $5.00 | $4.11 | $4.12 | $4.10 |
| 632E70001 POWER SERVICE, AS PER PLAN | 1 EACH | $13,168 | $12,472 | $10,000 | $12,690 | $12,713 | $12,645 |
| 632E77053 COMBINATION SIGNAL SUPPORT, TYPE TC-81.21 DESIGN 4 | 1 EACH | $12,855 | $12,176 | $11,200 | $12,389 | $12,412 | $12,345 |
| 632E77113 COMBINATION SIGNAL SUPPORT, TYPE TC-81.21 DESIGN 1 | 1 EACH | $15,566 | $14,743 | $13,425 | $15,001 | $15,028 | $14,947 |
| 632E77173 COMBINATION SIGNAL SUPPORT, TYPE TC-12.30 DESIGN 6 | 1 EACH | $17,681 | $16,747 | $16,825 | $17,040 | $17,071 | $16,979 |
| 632E80403 SIGNAL SUPPORT, TYPE TC-81.21, DESIGN 4, AS PER PL | 1 EACH | $10,640 | $10,078 | $8,900 | $10,254 | $10,272 | $10,217 |
| 632E81071 COMBINATION SIGNAL SUPPORT, TYPE TC-81.21, DESIGN | 3 EACH | $12,862 | $12,182 | $9,000 | $12,395 | $12,418 | $12,351 |
| 632E89905 PEDESTAL, 10', TRANSFORMER BASE, AS PER PLAN | 3 EACH | $984 | $931 | $1,050 | $1,000 | $950 | $944 |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 1 EACH | $2,534 | $2,400 | $9,000 | $2,442 | $2,446 | $2,433 |
| 633E67101 CABINET FOUNDATION, AS PER PLAN | 2 EACH | $2,604 | $2,467 | $4,750 | $2,509 | $2,514 | $2,500 |
| 633E67201 CONTROLLER WORK PAD, AS PER PLAN | 2 EACH | $562 | $533 | $1,100 | $542 | $543 | $540 |
| 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 2 EACH | $6,223 | $5,894 | $5,300 | $6,000 | $6,008 | $5,976 |
| 633E99000 CONTROLLER ITEM, MISC.: CONTROLLER UNIT, TYPE COBA | 2 EACH | $16,601 | $15,724 | $15,100 | $16,000 | $16,028 | $15,942 |
| 809E69000 ADVANCE RADAR DETECTION | 3 EACH | $8,594 | $8,140 | $7,000 | $8,300 | $8,297 | $8,253 |
| 809E69100 STOP LINE RADAR DETECTION | 8 EACH | $8,087 | $7,660 | $6,000 | $8,000 | $7,808 | $7,766 |
| AA2 633E67301 PREEMPTION, AS PER PLAN (GTT OPTICOM) (ALTERNATE 2 | 1 EACH | $91,184 | $91,328 | $39,000 | $86,364 | $88,035 | $87,559 |
| 410E12000 TRAFFIC COMPACTED SURFACE, TYPE A OR B | 25 CY | $96.25 | $84.00 | $60.00 | $63.00 | $130 | $70.94 |
| 410E13000 TRAFFIC COMPACTED SURFACE, TYPE C | 25 CY | $96.25 | $73.00 | $65.00 | $70.00 | $137 | $78.91 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 24 HOUR | $79.19 | $72.00 | $81.00 | $80.00 | $77.00 | $97.50 |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL (COLUMBUS RD. & | 1 EACH | $41,503 | $39,310 | $17,000 | $39,310 | $4,000 | $39,854 |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL (COLUMBUS RD. & | 1 EACH | $39,814 | $37,810 | $60,000 | $37,710 | $4,000 | $38,232 |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL (COLUMBUS RD. & | 1 EACH | $36,647 | $34,710 | $59,500 | $34,710 | $4,000 | $35,190 |
| 614E11300 SPECIAL - WORK ZONE TRAFFIC SIGNAL (S.R. 37/S.R. 6 | 1 EACH | $70,103 | $66,400 | $145,000 | $66,398 | $4,000 | $67,317 |
| 614E12336 WORK ZONE IMPACT ATTENUATOR (UNIDIRECTIONAL), 24" | 8 EACH | $2,112 | $2,000 | $1,840 | $2,000 | $1,931 | $1,895 |
| 614E12338 WORK ZONE IMPACT ATTENUATOR (BIDIRECTIONAL), 24" | 3 EACH | $2,112 | $2,000 | $1,840 | $2,000 | $1,931 | $1,895 |
| 614E12421 DETOUR SIGNING, AS PER PLAN | 1 LS | $18,646 | $24,500 | $40,000 | $20,000 | $17,660 | $18,800 |
| 614E12600 REPLACEMENT DRUM | 25 EACH | $84.46 | $65.00 | $60.00 | $80.00 | $80.00 | $65.00 |
| 614E13000 ASPHALT CONCRETE FOR MAINTAINING TRAFFIC | 50 CY | $282 | $200 | $225 | $300 | $350 | $150 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (BIDIRECTIONAL) | 64 EACH | $27.98 | $8.00 | $8.00 | $26.50 | $26.50 | $26.50 |
| 614E13310 BARRIER REFLECTOR, TYPE 1 (UNIDIRECTIONAL) | 40 EACH | $35.90 | $8.00 | $8.00 | $34.00 | $34.00 | $34.00 |
| 614E13350 OBJECT MARKER, ONE WAY | 39 EACH | $42.23 | $15.00 | $11.00 | $14.00 | $40.00 | $40.00 |
| 614E13360 OBJECT MARKER, TWO WAY | 56 EACH | $35.90 | $15.00 | $20.00 | $15.00 | $34.00 | $34.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 64 SNMT | $1,584 | $900 | $1,000 | $800 | $552 | $650 |
| 614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT | 1.81 MILE | $3,247 | $2,060 | $1,465 | $1,465 | $1,465 | $3,562 |
| 614E22100 WORK ZONE EDGE LINE, CLASS I, 4", 642 PAINT | 6.34 MILE | $1,425 | $1,275 | $740 | $740 | $740 | $1,564 |
| 614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT | 0.17 MILE | $13,594 | $1,665 | $840 | $840 | $840 | $14,915 |
| 614E23200 WORK ZONE CHANNELIZING LINE, CLASS I, 8", 642 PAIN | 208 FT | $5.28 | $0.80 | $0.95 | $0.95 | $0.95 | $5.79 |
| 614E24200 WORK ZONE DOTTED LINE, CLASS I, 4", 642 PAINT | 2,134 FT | $1.58 | $0.60 | $0.95 | $0.95 | $0.95 | $1.74 |
| 614E26200 WORK ZONE STOP LINE, CLASS I, 642 PAINT | 493 FT | $8.45 | $4.00 | $3.75 | $3.75 | $3.75 | $9.27 |
| 614E30200 WORK ZONE ARROW, CLASS I, 642 PAINT | 1 EACH | $396 | $175 | $80.00 | $80.00 | $80.00 | $434 |
| 614E31200 WORK ZONE WORD ON PAVEMENT, 72", CLASS I, 642 PAIN | 1 EACH | $396 | $175 | $95.00 | $95.00 | $95.00 | $434 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $18,401 | $27,500 | $22,500 | $25,000 | $133,000 | $23,138 |
| 615E20001 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A, AS PER | 781 SY | $48.50 | $105 | $55.00 | $62.00 | $55.00 | $64.65 |
| 616E10000 WATER | 155.2 MGAL | $37.43 | $115 | $75.00 | $35.00 | $200 | $11.64 |
| 622E41000 PORTABLE BARRIER, 32" | 4,309 FT | $20.11 | $18.00 | $12.00 | $18.00 | $16.00 | $31.90 |
| 622E41020 PORTABLE BARRIER, 32", BRIDGE MOUNTED | 750 FT | $20.47 | $18.00 | $18.00 | $20.00 | $22.50 | $44.47 |
| 202E22900 APPROACH SLAB REMOVED | 133 SY | $72.72 | $28.00 | $50.00 | $36.00 | $35.00 | $48.26 |
| 202E38500 BRIDGE RAILING REMOVED | 528 FT | $5.47 | $6.00 | $10.00 | $5.00 | $20.00 | $5.78 |
| 203E20000 EMBANKMENT | 2,032 CY | $15.16 | $13.00 | $10.00 | $15.00 | $8.00 | $12.91 |
| 203E35110 GRANULAR MATERIAL, TYPE B | 681 CY | $49.42 | $58.00 | $45.00 | $77.00 | $60.00 | $66.59 |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $110,860 | $14,500 | $75,000 | $80,000 | $95,000 | $8,735 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $13,710 | $11,338 | $50,000 | $25,000 | $9,500 | $7,463 |
| 505E11100 PILE DRIVING EQUIPMENT MOBILIZATION | 1 LS | $36,953 | $26,409 | $35,000 | $20,000 | $35,000 | $35,258 |
| 507E00600 14" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 3,000 FT | $14.78 | $22.00 | $27.50 | $19.00 | $14.00 | $35.69 |
| 507E00700 16" CAST-IN-PLACE REINFORCED CONCRETE PILES, DRIVE | 840 FT | $16.89 | $33.00 | $30.00 | $28.00 | $15.00 | $42.40 |
| 507E00750 16" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 980 FT | $65.46 | $34.00 | $35.00 | $44.00 | $58.50 | $52.25 |
| 511E41012 CLASS QC1 CONCRETE WITH QC/QA, PIER ABOVE FOOTINGS | 51 CY | $1,056 | $1,256 | $1,300 | $1,200 | $850 | $1,117 |
| 511E45723 CLASS QC SCC CONCRETE WITH QC/QA, ABUTMENT, AS PER | 70 CY | $871 | $1,135 | $1,300 | $860 | $735 | $1,476 |
| 511E46512 CLASS QC1 CONCRETE WITH QC/QA, FOOTING | 207 CY | $449 | $490 | $450 | $465 | $325 | $653 |
| 512E10050 SEALING OF CONCRETE SURFACES (NON-EPOXY) | 1,666 SY | $10.56 | $9.00 | $10.25 | $8.00 | $10.00 | $8.14 |
| 512E33000 TYPE 2 WATERPROOFING | 101 SY | $42.23 | $21.00 | $100 | $16.00 | $41.67 | $23.15 |
| 513E20000 WELDED STUD SHEAR CONNECTORS | 3,984 EACH | $3.48 | $3.45 | $3.25 | $3.50 | $3.30 | $8.21 |
| 514E10000 FINAL INSPECTION REPAIR | 14 EACH | $264 | $105 | $258 | $100 | $100 | $250 |
| 516E13601 1" PREFORMED EXPANSION JOINT FILLER, AS PER PLAN | 18 SF | $21.12 | $25.00 | $12.50 | $30.00 | $13.00 | $4.47 |
| 516E13901 2" PREFORMED EXPANSION JOINT FILLER, AS PER PLAN | 55 SF | $21.12 | $21.00 | $15.00 | $28.00 | $14.00 | $6.80 |
| 516E14020 SEMI-INTEGRAL ABUTMENT EXPANSION JOINT SEAL | 156 FT | $42.23 | $27.00 | $42.00 | $35.00 | $31.00 | $40.81 |
| 516E14600 STRUCTURAL JOINT OR JOINT SEALER, MISC.: EMSEAL WI | 140 FT | $264 | $283 | $400 | $300 | $150 | $244 |
| 516E44300 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 16 EACH | $2,163 | $1,524 | $1,750 | $2,100 | $2,100 | $2,400 |
| 516E44300 ELASTOMERIC BEARING WITH INTERNAL LAMINATES AND LO | 8 EACH | $2,438 | $1,512 | $1,350 | $1,800 | $1,700 | $2,005 |
| 518E21200 POROUS BACKFILL WITH GEOTEXTILE FABRIC | 92 CY | $90.54 | $64.00 | $125 | $106 | $91.00 | $94.40 |
| 523E20000 DYNAMIC LOAD TESTING | 2 EACH | $3,695 | $3,600 | $6,000 | $3,000 | $3,500 | $9,746 |
| 840E21000 WALL EXCAVATION | 4,242 CY | $7.07 | $12.00 | $17.50 | $15.00 | $11.00 | $26.61 |
| 840E22000 FOUNDATION PREPARATION | 713 SY | $76.62 | $27.00 | $25.00 | $21.00 | $30.00 | $34.02 |
| 840E23050 NATURAL SOIL | 666 CY | $19.53 | $17.00 | $20.00 | $20.00 | $16.00 | $22.61 |
| 840E25010 6" DRAINAGE PIPE, PERFORATED | 894 FT | $7.34 | $3.00 | $10.00 | $9.00 | $10.00 | $6.59 |
| 840E25020 6" DRAINAGE PIPE, NON-PERFORATED | 18 FT | $40.47 | $40.00 | $15.00 | $35.00 | $20.00 | $11.31 |
| 840E26001 CONCRETE COPING, AS PER PLAN | 391 FT | $139 | $199 | $200 | $210 | $110 | $286 |
| 840E26050 AESTHETIC SURFACE TREATMENT | 6,984 SF | $5.28 | $5.30 | $6.50 | $6.00 | $5.00 | $8.14 |
| 840E27000 ON-SITE ASSISTANCE | 5 DAY | $264 | $529 | $500 | $500 | $250 | $0.02 |
| 867E00100 TEMPORARY WIRE FACED MECHANICALLY STABILIZED EARTH | 1 LS | $62,757 | $110,000 | $130,000 | $100,000 | $65,000 | $62,925 |
| 100E50200 DEPARTMENT'S SHARE OF THE DISPUTE RESOLUTION ADVIS | 1 LS | $29,000 | $29,000 | $29,000 | $29,000 | $29,000 | $29,000 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $100,143 | $50,600 | $45,000 | $40,000 | $50,000 | $43,542 |
| 108E10000 CPM PROGRESS SCHEDULE | 1 LS | $12,670 | $6,000 | $3,500 | $10,000 | $30,000 | $9,944 |
| 111E10000 SPECIAL - DEPARTMENTS SHARE FACILITATED PARTNERING | 1 LS | $6,250 | $6,250 | $6,250 | $6,250 | $6,250 | $6,250 |
| 619E16020 FIELD OFFICE, TYPE C | 19 MNTH | $2,003 | $3,000 | $2,500 | $3,500 | $2,080 | $2,324 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $68,627 | $115,000 | $80,000 | $200,000 | $101,000 | $65,000 |
| 614E15000 SPECIAL - CALENDAR DAYS OF CONTRACT TIME FOR OPENI | 1,500 DLR | $28.00 | $28.00 | $21.00 | $28.00 | $28.00 | $38.96 |
| 614E15000 SPECIAL - CALENDAR DAYS OF CONTRACT TIME FOR OPENI | 500 DLR | $21.00 | $21.00 | $14.00 | $18.00 | $21.00 | $26.97 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 452E13020 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P W | 12,550 SY | $58.65 | $736k | 8% |
| 513E10040 STRUCTURAL STEEL MEMBERS, LEVEL 2 | 1 LS | $701,456 | $701k | 8% |
| 511E34447 CLASS QC2 CONCRETE WITH QC/QA, BRIDGE DECK, AS PER | 406 CY | $897.43 | $364k | 4% |
| 840E20001 MECHANICALLY STABILIZED EARTH WALL, AS PER PLAN | 6,984 SF | $50.31 | $351k | 4% |
| 203E20000 EMBANKMENT | 27,750 CY | $11.47 | $318k | 4% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 1,130 CY | $179.49 | $203k | 2% |
| 840E23000 SELECT GRANULAR BACKFILL | 3,941 CY | $49.19 | $194k | 2% |
| 624E10000 MOBILIZATION | 1 LS | $186,108 | $186k | 2% |
| 507E00650 14" CAST-IN-PLACE REINFORCED CONCRETE PILES, FURNI | 3,300 FT | $55.96 | $185k | 2% |
| 304E20000 AGGREGATE BASE | 3,399 CY | $53.61 | $182k | 2% |