CLI-IR 71-11.21 Weigh Station
CLI County · est $1.5M
Bid dateThursday, April 27—
CLI County · est $1.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 39 more items below.
| Item | Quantity | R1R B Jergens Contractors INC | R2Axis Civil Construction LLC | R3Sunesis Construction CO | R4John R Jurgensen Company | R5Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|---|
| 452E13010 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 8,237 SY | $94.04 | $100 | $111 | $117 | $130 | 53% |
| 204E30021 GRANULAR MATERIAL, TYPE C, AS PER PLAN | 3,206 CY | $55.61 | $64.00 | $64.31 | $52.18 | $50.00 | 12% |
| 204E13000 EXCAVATION OF SUBGRADE | 3,206 CY | $23.03 | $23.80 | $46.31 | $32.45 | $25.00 | 5% |
| 304E20000 AGGREGATE BASE | 1,371 CY | $48.31 | $70.00 | $58.46 | $60.03 | $70.00 | 5% |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 3,115 FT | $18.15 | $14.41 | $11.22 | $21.79 | $15.00 | 4% |
| 624E10000 MOBILIZATION |
| Item | Quantity | R1R B Jergens Contractors INC | R2Axis Civil Construction LLC | R3Sunesis Construction CO | R4John R Jurgensen Company | R5Complete General Construction Company |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $6,463 | $10,000 | $863 | $10,211 | $10,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 101 FT | $20.82 | $20.00 | $16.15 | $63.20 | $40.00 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $239 | $1,000 | $488 | $356 | $850 |
| 202E66000 SPECIAL - DRILLED WATER WELL ABANDONED | 1 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 1 LS |
| $47,355 |
| $30,000 |
| $48,087 |
| $40,000 |
| $40,000 |
| 3% |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $27,462 | $17,500 | $16,574 | $15,300 | $15,000 | 2% |
| 204E50000 GEOTEXTILE FABRIC | 8,585 SY | $2.95 | $1.10 | $1.65 | $2.41 | $1.50 | 2% |
| 203E10000 EXCAVATION | 1,375 CY | $16.21 | $23.80 | $49.29 | $39.72 | $36.00 | 2% |
| 202E23000 PAVEMENT REMOVED | 6,681 SY | $3.33 | $10.00 | $15.36 | $11.74 | $12.00 | 2% |
| 646E50100 REMOVAL OF PAVEMENT MARKING | 2,057 FT | $10.57 | $2.10 | $1.50 | $1.50 | $1.50 | 2% |
| 690E98400 SPECIAL - CONSULTANT FOR CONCRETE QUALITY CONTROL | 1 LS | $20,655 | $22,000 | $12,011 | $23,251 | $35,000 | 1% |
| 646E10010 EDGE LINE, 6" | 1.19 MILE | $15,898 | $3,500 | $3,400 | $3,400 | $3,400 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $16,937 | $5,000 | $3,557 | $27,715 | $7,000 | 1% |
| 659E00300 TOPSOIL | 336 CY | $50.22 | $32.00 | $33.09 | $5.00 | $62.00 | 1% |
| 204E10000 SUBGRADE COMPACTION | 8,585 SY | $1.80 | $2.00 | $2.48 | $1.73 | $2.00 | 1% |
| 646E20200 PARKING LOT STALL MARKING | 1,754 FT | $7.40 | $3.10 | $2.00 | $2.00 | $2.00 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $12,822 | $10,000 | $10,326 | $8,540 | $13,000 | 1% |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 1% |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $8,456 | $5,600 | $4,267 | $3,450 | $5,000 | 1% |
| $3,971 |
| $5,500 |
| $5,000 |
| $15,938 |
| $2,000 |
| 202E98100 REMOVAL MISC.: BOLLARD | 3 EACH | $93.25 | $100 | $127 | $239 | $275 |
| 202E98100 REMOVAL MISC.: BUILDING FOUNDATION | 1 EACH | $6,082 | $10,000 | $5,828 | $14,079 | $20,000 |
| 202E98100 REMOVAL MISC.: SCALE FRAME | 1 EACH | $3,050 | $1,000 | $3,223 | $3,341 | $4,000 |
| 204E45000 PROOF ROLLING | 5 HOUR | $308 | $200 | $246 | $207 | $335 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 12 SY | $197 | $70.00 | $136 | $193 | $155 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $423 | $80.00 | $80.00 | $175 | $175 |
| 659E10000 SEEDING AND MULCHING | 2,237 SY | $1.85 | $3.75 | $4.89 | $2.30 | $2.30 |
| 659E14000 REPAIR SEEDING AND MULCHING | 112 SY | $1.06 | $14.00 | $14.00 | $2.30 | $2.30 |
| 659E20000 COMMERCIAL FERTILIZER | 0.3 TON | $1,586 | $950 | $950 | $975 | $975 |
| 659E31000 LIME | 0.46 ACRE | $211 | $25.00 | $25.00 | $150 | $150 |
| 659E35000 WATER | 12 MGAL | $1.06 | $5.00 | $5.00 | $1.00 | $1.00 |
| 670E00700 DITCH EROSION PROTECTION | 787 SY | $2.48 | $2.00 | $2.00 | $3.20 | $3.20 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,586 | $1,475 | $1,475 | $1,475 | $2,500 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $5,285 | $5,113 | $4,437 | $4,437 | $4,400 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 153 FT | $21.71 | $22.00 | $38.70 | $36.18 | $38.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 5 EACH | $537 | $300 | $485 | $572 | $520 |
| 617E10100 COMPACTED AGGREGATE | 126 CY | $62.98 | $90.00 | $81.55 | $107 | $90.00 |
| 617E25000 WATER | 4 MGAL | $222 | $1.00 | $17.93 | $50.98 | $200 |
| 621E00100 RPM | 41 EACH | $77.17 | $90.00 | $73.00 | $73.00 | $73.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 25 EACH | $11.98 | $15.00 | $73.00 | $22.22 | $30.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 457 FT | $15.77 | $17.50 | $14.92 | $17.50 | $14.92 |
| 630E07000 GROUND MOUNTED STRUCTURAL BEAM SUPPORT, W8X18 | 148 FT | $38.66 | $50.00 | $36.57 | $50.00 | $36.57 |
| 630E08600 SIGN POST REFLECTOR | 8 EACH | $58.52 | $48.25 | $55.36 | $48.25 | $55.36 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 6 EACH | $484 | $825 | $458 | $825 | $458 |
| 630E80100 SIGN, FLAT SHEET | 155 SF | $19.66 | $25.00 | $18.60 | $25.00 | $18.60 |
| 630E80200 SIGN, GROUND MOUNTED EXTRUSHEET | 276 SF | $25.34 | $30.00 | $23.97 | $30.00 | $23.97 |
| 630E84500 GROUND MOUNTED STRUCTURAL BEAM SUPPORT FOUNDATION | 6 EACH | $946 | $1,500 | $895 | $1,500 | $895 |
| 646E10310 CHANNELIZING LINE, 12" | 1,052 FT | $5.29 | $2.00 | $2.00 | $2.00 | $2.00 |
| 646E10600 TRANSVERSE/DIAGONAL LINE | 213 FT | $7.40 | $8.00 | $7.00 | $7.00 | $7.00 |
| 646E10620 CHEVRON MARKING | 410 FT | $15.86 | $8.00 | $10.00 | $10.00 | $10.00 |
| 646E20320 WRONG WAY ARROW | 2 EACH | $423 | $280 | $300 | $300 | $300 |
| 646E20504 DOTTED LINE, 6" | 1,621 FT | $3.12 | $2.30 | $2.60 | $2.60 | $2.60 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $116 | $75.00 | $80.00 | $89.17 | $95.00 |
| 616E10000 WATER | 13 MGAL | $123 | $1.00 | $11.03 | $55.00 | $90.00 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $8,086 | $10,000 | $9,700 | $6,741 | $25,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 452E13010 9" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC 1P | 8,237 SY | $94.04 | $775k | 49% |
| 204E30021 GRANULAR MATERIAL, TYPE C, AS PER PLAN | 3,206 CY | $55.61 | $178k | 11% |
| 204E13000 EXCAVATION OF SUBGRADE | 3,206 CY | $23.03 | $74k | 5% |
| 304E20000 AGGREGATE BASE | 1,371 CY | $48.31 | $66k | 4% |
| 605E13300 6" UNCLASSIFIED PIPE UNDERDRAINS | 3,115 FT | $18.15 | $57k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $47,355 | $47k | 3% |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $27,462 | $27k | 2% |
| 204E50000 GEOTEXTILE FABRIC | 8,585 SY | $2.95 | $25k | 2% |
| 203E10000 EXCAVATION | 1,375 CY | $16.21 | $22k | 1% |
| 202E23000 PAVEMENT REMOVED | 6,681 SY | $3.33 | $22k | 1% |